Section A: Industrial Management

Question 1

(a) Describe three industrial disputes that may arise in a manufacturing organization. (6 marks)

  1. Wage dispute: Employees and management may disagree over pay rates, allowances, bonuses or overtime payments.
  2. Working-conditions dispute: Conflict may concern hours of work, safety, workload, leave or the physical work environment.
  3. Disciplinary or employment dispute: Employees may contest dismissal, redundancy, promotion, transfer or disciplinary action.

(b) Explain three costs associated with plant maintenance. (6 marks)

  1. Labour cost: Wages, overtime and specialist fees are incurred for inspection, servicing and repairs.
  2. Materials and spare-parts cost: Lubricants, replacement components, tools and consumables must be purchased and stored.
  3. Downtime cost: Production and contribution are lost while equipment is stopped for planned or emergency maintenance.

(c) Describe four challenges that may be faced by a production plant. (8 marks)

  1. Equipment breakdown: Unreliable machinery interrupts output and raises repair costs.
  2. Input shortages: Delayed or poor-quality raw materials prevent continuous production.
  3. Power and utility interruptions: Unstable electricity, water or fuel supplies cause stoppages and damaged output.
  4. Labour and quality problems: Skill shortages, absenteeism or weak process control reduce productivity and increase rejects.

Back to top ↑

Question 2

(a) State four obligations of a manufacturing organization to its competitors. (4 marks)

  1. Compete fairly and comply with competition laws.
  2. Avoid false advertising, defamation and misleading comparisons.
  3. Respect competitors’ patents, trademarks, copyrights and trade secrets.
  4. Avoid collusion, sabotage, industrial espionage and other unethical practices.

(b) (i) Explain the concept of administration as applied to management.

Administration is the process of formulating organizational objectives and policies and coordinating people, information and other resources so those policies are implemented effectively.

(ii) Highlight four situations when good leadership is required in an organization. (6 marks total)

  1. During a crisis or emergency that requires clear direction.
  2. When introducing major organizational or technological change.
  3. When employee morale, motivation or productivity is low.
  4. When resolving conflict or coordinating a new or diverse team.

(c) List four advertising media used by industrial organizations. (4 marks)

  1. Television.
  2. Radio.
  3. Newspapers and magazines.
  4. Websites, search engines and social media.

(d) Explain three reasons performance contracting has become popular in modern organizations. (6 marks)

  1. Clear targets: It translates organizational goals into measurable commitments and expected results.
  2. Accountability: Managers and employees can be assessed against agreed indicators, making responsibility clearer.
  3. Improved efficiency and motivation: Monitoring results and linking them to recognition or corrective action encourages better use of resources.

Back to top ↑

Question 3

(a) Outline four duties performed by office staff. (4 marks)

  1. Preparing, receiving and filing correspondence and records.
  2. Answering telephone calls and attending to visitors.
  3. Entering, processing and retrieving organizational information.
  4. Scheduling meetings and supporting routine administrative work.

(b) Describe three monetary-policy instruments used by the Central Bank to control money supply. (6 marks)

  1. Open-market operations: Selling government securities withdraws money from circulation, while buying them injects money.
  2. Central-bank or policy rate: Raising the rate makes bank credit more expensive and restrains borrowing; lowering it encourages credit.
  3. Cash-reserve requirement: Increasing the proportion banks must hold reduces their lending capacity, while reducing it expands lending.

(c) Production-project network analysis. (10 marks)

Table 1: Activities and durations
Activity Duration (days) Earliest start Latest finish Total float
1-2 3 0 9 6
1-3 4 0 4 0
1-4 2 0 11 9
2-5 5 3 14 6
3-6 9 4 14 1
3-7 8 4 12 0
4-6 3 2 14 9
5-8 2 8 16 6
6-9 5 13 19 1
7-8 4 12 16 0
8-9 3 16 19 0

(i) Network diagram

1 --3d--> 2 --5d--> 5 --2d--> 8 --3d--> 9
|                              ^
|--4d--> 3 --8d--> 7 --4d-------|   CRITICAL
|          |
|          +--9d--> 6 --5d--------------> 9
|                    ^
+--2d--> 4 --3d------|

(ii) Critical path, duration and float

Longest path = 1-3-7-8-9

Critical path duration = 4 + 8 + 4 + 3 = 19 days

Non-critical activity floats: 1-2 = 6; 1-4 = 9; 2-5 = 6; 3-6 = 1; 4-6 = 9; 5-8 = 6; 6-9 = 1 day.

Back to top ↑

Section B: Estimating, Tendering and Engineering Services Contracts

Question 4

(a) Describe three acts of negligence that a contractor may commit at a project site. (6 marks)

  1. Failing to provide safe access, protective equipment, barriers or warnings around hazards.
  2. Using defective materials or carrying out work below the specified standard.
  3. Failing to supervise workers or protect neighbouring property and the public from foreseeable harm.

(b) Highlight three challenges of settling contractual disputes through courts. (6 marks)

  1. Delay: Formal procedure, congested court calendars and appeals may take a long time.
  2. High cost: Legal representation, expert witnesses and court fees can be expensive.
  3. Adversarial and public process: Litigation may damage business relationships and expose confidential information.

(c) Describe four requirements used to determine an individual’s capacity to contract. (8 marks)

  1. Age of majority: The person should have attained the legal age required to enter a binding contract.
  2. Sound mind: The person must understand the nature and consequences of the transaction.
  3. Sobriety and free judgement: Severe intoxication should not prevent the person from understanding the agreement.
  4. No legal disqualification: The person must not be barred by law, for example through relevant bankruptcy or other statutory restriction.

Back to top ↑

Question 5

(a) Outline six clauses that should be contained in the schedule of conditions of a construction contract. (6 marks)

  1. Date for possession or commencement.
  2. Contract period and completion date.
  3. Liquidated damages for delay.
  4. Defects-liability period.
  5. Retention percentage and limit.
  6. Insurance, performance security and payment particulars.

(b) Explain three methods of discharging contracts. (6 marks)

  1. Performance: Both parties fully carry out their contractual obligations.
  2. Agreement: The parties mutually agree to cancel, vary, replace or release each other from the contract.
  3. Breach or frustration: A serious breach may entitle the innocent party to terminate, while an unforeseen event making performance impossible may discharge both parties.

(c) (i) Explain two circumstances when cost-reimbursement contracting can be applied.

  1. Emergency work where construction must start before a complete design and firm price can be prepared.
  2. Complex or uncertain work where scope, quantities or site conditions cannot be reliably defined in advance.

(ii) State four limitations of a cost-reimbursement contract to the client. (8 marks total)

  1. The final contract cost is uncertain at the start.
  2. The contractor has less incentive to minimize expenditure.
  3. Detailed checking and auditing of allowable costs increases administration.
  4. Disputes may arise over whether particular costs are reasonable and reimbursable.

Back to top ↑

Question 6

(a) State four reasons that may lead to rejection of a tender document. (4 marks)

  1. Submission after the closing deadline.
  2. Missing signature, tender security or mandatory document.
  3. Material failure to comply with specifications or tender conditions.
  4. Evidence of falsification, collusion, conflict of interest or an abnormally unreliable price.

(b) Explain four benefits of open tendering to an organization. (8 marks)

  1. Wide competition: Any qualified supplier may bid, increasing the number and range of offers.
  2. Better value: Competitive pressure can produce favourable prices and stronger technical proposals.
  3. Transparency: Public advertisement and common criteria strengthen fairness and accountability.
  4. New supplier opportunities: The organization can discover capable contractors outside its usual list.

(c) Describe four methods of allocating overhead costs to a project estimate. (8 marks)

  1. Percentage of direct labour: Apply an overhead percentage to estimated labour cost.
  2. Percentage of material cost: Recover overhead as a percentage of the project’s direct material cost.
  3. Percentage of prime cost: Apply a rate to the combined direct labour, materials and other direct expenses.
  4. Time or activity rate: Allocate overhead using labour hours, machine hours or project duration according to resource consumption.

Back to top ↑

Question 7

(a) Explain three ways a contractor may obtain quotations from potential material suppliers. (6 marks)

  1. Written request for quotation: Send suppliers a schedule of required quantities, specifications and delivery terms.
  2. Electronic enquiry: Request and receive quotations through email, supplier websites or procurement portals.
  3. Direct enquiry: Visit or telephone suppliers to obtain current prices, discounts, availability and delivery information.

(b) Describe three measures a contractor may take to avoid purchasing defective materials. (6 marks)

  1. Purchase from prequalified, reputable suppliers with reliable quality records.
  2. Issue precise specifications and require approved samples, warranties and test certificates.
  3. Inspect and, where necessary, test materials before acceptance or payment and reject nonconforming deliveries.

(c) Describe four methods of reporting work progress at a site. (8 marks)

  1. Written progress reports: Daily, weekly or monthly reports summarize work completed, resources, delays and planned actions.
  2. Site meetings and minutes: Progress is presented to project parties and agreed decisions are formally recorded.
  3. Updated programmes: Bar charts, milestone schedules or network programmes compare actual progress with planned dates.
  4. Photographic records: Dated photographs or videos provide visible evidence of physical progress and site conditions.

Back to top ↑

Question 8

(a) List four office overheads for a project. (4 marks)

  1. Office rent and rates.
  2. Administrative staff salaries.
  3. Electricity, water, telephone and internet charges.
  4. Stationery, printing, postage and general office supplies.

(b) Highlight six activities that should be performed when preparing for a construction site meeting. (6 marks)

  1. Fix the date, time and venue.
  2. Notify all required participants in good time.
  3. Prepare and circulate the agenda.
  4. Review the previous minutes and outstanding action points.
  5. Collect progress reports, drawings, instructions, certificates and other relevant documents.
  6. Inspect the site and identify matters requiring discussion.

(c) Technicians demand an increase in wages. Describe five measures the project manager should take to resolve the conflict. (10 marks)

  1. Acknowledge the dispute and maintain calm: Arrange orderly representation and discourage threats, victimization or unsafe disruption.
  2. Listen to both sides: Meet technician representatives and management separately or jointly to identify the real issues and interests.
  3. Establish the facts: Review employment contracts, wage agreements, legal minimums, market rates, productivity and project affordability.
  4. Negotiate a fair solution: Explore wage adjustments, allowances, phased increases or productivity-linked arrangements; use mediation if necessary.
  5. Document and implement the agreement: Record responsibilities and dates, communicate the outcome, restore work and monitor compliance.

Back to top ↑