Shorten a project by recalculating the critical path

In project scheduling, crashing means paying an additional direct cost to reduce an activity’s duration within its allowed limit. Under a linear cost assumption, slope = (crash cost − normal cost)/(normal duration − crash duration). Only shortening activities that constrain the finish can shorten the whole project. Recalculate all relevant path lengths after each reduction because a second path may become critical.

Worked practice example

Two paths run from start to finish: A–B takes 4 + 6 = 10 days; C–D takes 3 + 5 = 8 days. A can be shortened from 4 to 3 days for KSh 500. B can be shortened from 6 to 4 days for KSh 1,600 total. Find the cheapest way to finish in 8 days under these linear assumptions.

Step Working
Critical path initially A–B is 10 days; C–D is 8 days.
Crash slopes A: 500/(4 − 3) = KSh 500/day. B: 1600/(6 − 4) = KSh 800/day.
First reduction Shorten A by one day: A–B becomes 9 days, extra cost KSh 500.
Second reduction Shorten B by one day: both paths become 8 days. Total extra cost = 500 + 800 = KSh 1,300.

Check your method

Crashing B by two days would also meet 8 days but cost KSh 1,600. Crashing C or D initially would not shorten the 10-day path. Once both paths are critical, shortening only A–B cannot reduce the project below 8 days.

Try it yourself

Would one more day taken from B alone reduce the project duration to 7 days?

Show the answer and method

No. A–B would become 7 days but C–D would remain 8 days, so project duration would remain 8 days. Every critical path must be shortened to reduce the finish time further.