Question 1(a) — 12 marks
Describe the steps that a project manager should follow in project planning.
Answer
- Define the project objectives, scope and measurable deliverables.
- Identify stakeholders, requirements, assumptions and constraints.
- Break the work into activities and establish their dependencies.
- Estimate durations, resource needs and costs, then prepare the schedule and budget.
- Identify risks and define quality, communication and procurement arrangements.
- Obtain approval, establish responsibilities and set progress-monitoring and change-control procedures.
Question 1(b) — 8 marks
One of the methods of awarding a project contract is through serial tenders. Outline the benefits of this method of tendering.
Answer
- Rates established through an initial competitive process can support pricing of later similar work.
- Repeated tender preparation and evaluation effort can be reduced.
- Continuity with a capable contractor can improve learning and working relationships.
- Earlier contractor availability and known pricing arrangements can speed mobilisation for comparable later phases.
Question 2(a) — 12 marks
Explain the responsibilities of a project manager in the execution of a project.
Answer
- Coordinate activities and ensure work follows the approved scope and schedule.
- Allocate and manage staff, materials, equipment and other project resources.
- Monitor expenditure and control commitments within authorised budgets.
- Verify quality and compliance with technical, safety and contractual requirements.
- Manage risks, issues, changes and relationships with contractors and stakeholders.
- Report progress and arrange acceptance, handover and closure of completed outputs.
Question 2(b) — 8 marks
Outline the demerits of single-sourcing as a method of awarding project contracts.
Answer
- Limited competition can lead to higher prices or less favourable terms.
- Dependence on one contractor increases exposure to failure or delay.
- Lack of alternative offers makes value-for-money comparison more difficult.
- Reduced transparency can create perceptions or risks of favouritism and weaken accountability.
Question 3(a) — 12 marks
A certain organization advertised for one of its project’s tender bids. Describe the types of documents that the firm should issue to contractors who respond to the advertisement.
Answer
- Instructions to tenderers explain submission, deadlines, clarification and evaluation procedures.
- Technical specifications and scope describe the required work and performance.
- Drawings and other design information clarify dimensions, interfaces and site requirements.
- Bills of quantities or pricing schedules provide a consistent basis for financial offers.
- Conditions and draft form of contract state responsibilities, payment, risk and dispute provisions.
- Tender and qualification forms request the bidder’s offer, capability evidence and required declarations or securities.
Question 3(b) — 8 marks
It is usually necessary to have a strong client-contractor collaboration when undertaking project work. Explain the reasons that may justify this requirement.
Answer
- Timely communication resolves unclear requirements before they cause rework.
- Joint coordination aligns access, approvals, supplies and work schedules.
- Early discussion of risks and changes supports practical solutions.
- Trust and transparent records reduce avoidable claims and improve acceptance and handover.
Question 4(a) — 10 marks
Highlight the factors that a firm should consider in determining the method of payment to a project contractor.
Answer
- Nature and measurability of the work determine whether milestones, quantities or reimbursable costs are appropriate.
- Allocation of cost and performance risk influences suitable payment incentives.
- Project duration and contractor cash-flow needs affect payment frequency.
- Available budget, financing and the client’s approval capability constrain feasible arrangements.
- Contract terms, verification requirements and relevant procurement obligations determine authorised payment conditions.
Question 4(b) — 10 marks
Explain the factors that may limit the effectiveness of the planning process for a project.
Answer
- Unclear objectives and incomplete scope make reliable activities and estimates difficult to define.
- Inaccurate information and unrealistic assumptions undermine schedules and budgets.
- Limited planning expertise, time or resources restrict the quality of analysis.
- Poor stakeholder participation can omit requirements and weaken commitment.
- Uncertainty and frequent external changes can invalidate the original plan.
Question 5(a) — 10 marks
There are certain factors that may trigger the need for a firm to undertake a project. Highlight these factors.
Answer
- New customer demand or an unmet market opportunity may require a new output.
- Operational inefficiency may justify process or equipment improvement.
- New technology may create an opportunity or a need to modernise.
- Legal, safety or environmental requirements may require a defined change.
- Corporate growth, replacement of ageing assets or response to disruption may require a temporary organised initiative.
Question 5(b) — 10 marks
One of the methods that a project manager may use in project planning is the Critical Path Analysis (CPA). Describe the types of information that the manager may obtain from the use of this method.
Answer
- A logical network shows the activities and their predecessor relationships.
- Earliest start and finish times show the soonest feasible activity schedule.
- Latest start and finish times show timing limits without delaying overall completion.
- The critical path identifies activities with no total float that determine project duration.
- Float for noncritical activities shows scheduling flexibility for resource allocation and delay management.
Question 6(a) — 10 marks
Highlight the typical cost components that should be considered in the planning stage of the project life cycle.
Answer
- Labour and professional-service costs cover the people needed to plan and deliver the work.
- Material and purchased-component costs cover items incorporated or consumed in the project.
- Plant, equipment and facility costs cover acquisition, hire, operation and maintenance.
- Administration, permits, insurance and other overheads support project execution.
- Contingency, commissioning and closure costs cover identified uncertainty and bringing the completed output into use.
Question 6(b) — 10 marks
Wavinya, a project manager is in the process of selecting project team members. Outline the factors that she should consider in selecting members to such a team.
Answer
- Relevant technical competence matches members to the project’s tasks.
- Experience with similar work improves practical judgement and problem-solving.
- Availability and workload determine whether members can meet the required commitment.
- Communication, cooperation and complementary skills support effective teamwork.
- Integrity, reliability and clear role representation support accountable project decisions.
Question 7(a) — 10 marks
One of the stages of a project life cycle is the feasibility analysis stage. Explain the issues that should be considered at this stage.
Answer
- Market or user demand indicates whether the proposed output meets a real need.
- Technical feasibility shows that suitable methods, skills and technology can deliver the output.
- Financial and economic appraisal compares expected benefits with investment and operating costs.
- Legal, environmental and social assessment identifies approvals, impacts and stakeholder acceptance.
- Resource, schedule and risk assessment tests whether the project can be implemented and sustained realistically.
Question 7(b) — 10 marks
Describe the activities that a contractor should undertake during the termination stage of a contract.
Answer
- Stop or complete work as directed under the valid termination arrangement and secure the site safely.
- Record completed work, materials, equipment and outstanding obligations.
- Prepare final accounts and resolve certified payments, claims and required deductions.
- Return client property and hand over relevant drawings, records, manuals and completed outputs.
- Demobilise staff and equipment, settle subcontract obligations and archive records while honouring any continuing contractual duties.